Alderton suggests telltale signs of project trouble.Match these terms for these signs with their descriptions.
A)Muddy waters
B)Unconstrained constraints
C)Suspicious status reports
D)Discord and drama
1)Knowing how much leeway there is in your schedule and budget for each task,and where delays or cost overruns can be made up,keeps a project out of trouble.
2)Vague or overly optimistic language such as "very soon" or "marginal increase" in costs also indicates trouble ahead.
3)Unhappy team members can cause major trouble in the project.
4)The scope is not well defined or well understood." Vague or incomplete project requirements are a major red flag.
Correct Answer:

Verified
Correct Answer:
Verified
Q10: There are several conventions used to aid
Q11: In earned value Analysis,the 0 - 100
Q12: What is the relationship between management level
Q13: There are several conventions used to aid
Q14: In earned value analysis,the _ is computed
Q16: List the four conventions used to aid
Q17: Which of the following is not a
Q18: If EV = $500,AC = $475,PV =
Q19: ETC + AC = _.<br>A)BAC<br>B)EAC<br>C)SPI<br>D)CPI