    What Is the Fastest Completion Time of the Project with Activity
Solved

What Is the Fastest Completion Time of the Project with Activity

Question 63

Question 63

Multiple Choice

What is the fastest completion time of the project with activity lengths (in days) and precedence requirements as shown in the table? What is the fastest completion time of the project with activity lengths (in days) and precedence requirements as shown in the table?   A)  22 B)  25 C)  27 D)  30


A) 22
B) 25
C) 27
D) 30

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Project planners develop a broad definition of

Q8: The professional organization that serves the needs

Q12: During the _, project planners identify how

Q24: The tablet unearthed by the archaeologist

Q26: In what ways are projects distinct from

Q29: A critical path is composed entirely of

Q60: Construction of the cattery could be distilled

Q62: A project is composed of 6 activities

Q64: A seven activity project has the activity

Q65: A seven activity project has the activity

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines