Multiple Choice
A seven activity project has the activity durations (in weeks) and costs shown in the table.In addition to the activity costs shown in the table,there is an additional daily fixed cost of $450.What is the least expensive project completion cost?
A) $31,450
B) $31,900
C) $32,350
D) $32,700