Solved

A Seven Activity Project Has the Activity Durations (In Weeks)and

Question 64

Multiple Choice

A seven activity project has the activity durations (in weeks) and costs shown in the table.In addition to the activity costs shown in the table,there is an additional daily fixed cost of $450.What is the least expensive project completion cost? A seven activity project has the activity durations (in weeks) and costs shown in the table.In addition to the activity costs shown in the table,there is an additional daily fixed cost of $450.What is the least expensive project completion cost?   A)  $31,450 B)  $31,900 C)  $32,350 D)  $32,700


A) $31,450
B) $31,900
C) $32,350
D) $32,700

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions