Multiple Choice
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following questions.
-Refer to the scenario above.One activity has identical earliest finish and latest start times.What is the common number for this unusual activity?
A) 17
B) 18
C) 21
D) 29
Correct Answer:

Verified
Correct Answer:
Verified
Q8: The professional organization that serves the needs
Q24: The tablet unearthed by the archaeologist
Q26: In what ways are projects distinct from
Q55: Complete this table containing earliest and latest
Q56: Crashing a project refers to the technique
Q57: The project shown below has crash costs
Q62: A project is composed of 6 activities
Q63: What is the fastest completion time of
Q64: A seven activity project has the activity
Q65: A seven activity project has the activity