Which of the following statements about CCPM activity networks is CORRECT?
A) Project workers are more likely to meet a deadline for their activity than miss it.
B) There are no milestones in the CCPM activity network.
C) Project workers are more likely to miss a deadline for their activity than meet it.
D) There is no project delivery deadline in the CCPM activity network.