Multiple Choice
A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Goldratt's model to determine the aggregated buffer for this project.
A) 20 days
B) 10 days
C) 15 days
D) 5 days
Correct Answer:

Verified
Correct Answer:
Verified