Question 9

Multiple Choice

A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Newbold's model to determine the aggregated buffer of one standard deviation for this project.  Activity  Average  Worst-Case X1220Y2025Z1424W1826\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Average } & \text { Worst-Case } \\\hline \mathrm { X } & 12 & 20 \\\hline \mathrm { Y} & 20 & 25 \\\hline \mathrm { Z} & 14 & 24 \\\hline \mathrm { W } & 18 & 26 \\\hline\end{array}


A) 31 days
B) 16 days
C) 8 days
D) 5 days