Solved

A Project Is Represented by the Activity Durations (Estimated at 90

Question 8

Multiple Choice

A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the feeder buffer for path NQT if this project is managed using critical chain methodology?  Activity  Predecessor  Length  Activity  Predecessor  Length M8R12N8 SP14PM12 TR,Q7QN10 V S, T11\begin{array}{|l|l|l|l|l|l|}\hline \text { Activity } & \text { Predecessor } & \text { Length } & \text { Activity } & \text { Predecessor } & \text { Length } \\\hline \mathrm{M} & - & 8 &\mathrm{R} & -- & 12 \\\hline \mathrm{N} & - & 8 & \mathrm{~S} & \mathrm{P} & 14 \\\hline \mathrm{P} & \mathrm{M} & 12 & \mathrm{~T} & \mathrm{R}, \mathrm{Q} & 7 \\\hline \mathrm{Q} & \mathrm{N} & 10 & \mathrm{~V} & \mathrm{~S}, \mathrm{~T} & 11\\ \hline \end{array}


A) 9.0
B) 2.25
C) 4.5
D) 6.75

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions