A Project Is Represented by the Activity Durations (In Days,estimated

Question 12

Multiple Choice

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach.  Activity  Predecessor  Lengenth  Activity  Predecessor  Length  A 18EC,D13B16FC9CA22GE,F15DB14\begin{array} { | l | l | l | l | l | l } \hline \text { Activity } & \text { Predecessor } & \text { Lengenth } & \text { Activity } & \text { Predecessor } & \text { Length } \\\hline \text { A } & - - & 18 & \mathrm { E} & \mathrm { C }, \mathrm { D} & 13 \\\hline B & - & 16 & \mathrm { F} & \mathrm { C }& 9 \\\hline \mathrm { C } & \mathrm { A } & 22 & \mathrm {G} & \mathrm { E } , \mathrm { F } & 15 \\\hline \mathrm { D } & \mathrm { B } & 14 & & & \\\hline\end{array}


A) 8.5 days
B) 17 days
C) 24.5 days
D) 34 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions