Question 33

Multiple Choice

Consider the project that is neatly summarized in this table.What are the lowest priority activities when using the smallest amount of slack leveling heuristic?  Activity  Duration  Predecessors  Workers Required A23B4 A 4C6 A 2D7 B5E9C,D,E2\begin{array} { | l | l | l | l | } \hline \text { Activity } & \text { Duration } & \text { Predecessors } & \text { Workers Required } \\\hline \mathrm {A } & 2 & - & 3 \\\hline \mathrm { B} & 4 & \text { A } & 4 \\\hline \mathrm { C } & 6 & \text { A } & 2 \\\hline \mathrm { D } & 7 & \mathrm {~B} & 5 \\\hline \mathrm { E } & 9 & \mathrm { C } , \mathrm { D },\mathrm { E } & 2 \\\hline\end{array}


A) A and B
B) C and E
C) A and D
D) B and D