Multiple Choice
Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day) to this project.Assume that the project work is conducted on a 5-day-per-week basis.
A) 30 hours
B) 20 hours
C) 40 hours
D) 36 hours
Correct Answer:

Verified
Correct Answer:
Verified