Solved

Use This Earned Schedule Table to Determine the Schedule Performance

Question 106

Multiple Choice

Use this earned schedule table to determine the schedule performance index (t) for this project at the end of Month 6.  Month 1  Month 2 Month 3 Month 4  Month 5 Month 6  Month 7 PV ($)  $125$275$500$875$1,485$2,325$2,670 EV ($)  $50$120$255$420$715$865$0\begin{array} { | l | l | l | l | l | l | l | l | } \hline & \text { Month 1 } & \text { Month } 2 & \text { Month } 3 & \text { Month 4 } & \text { Month } 5 & \text { Month 6 } & \text { Month } 7 \\\hline \text { PV (\$) } & \$ 125 & \$ 275 & \$ 500 & \$ 875 & \$ 1,485 & \$ 2,325 & \$ 2,670 \\\hline \text { EV (\$) } & \$ 50 & \$ 120 & \$ 255 & \$ 420 & \$ 715 & \$ 865 & \$ 0 \\\hline\end{array}


A) 0.71
B) 0.54
C) 0.38
D) 0.21

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions