Multiple Choice
Which of the following is not a format that is typically used to represent a Work Breakdown Structure?
A) Hierarchical
B) Indented outline
C) Requirements Traceability Matrix
D) Free Format
Correct Answer:

Verified
Correct Answer:
Verified