    An Undesirable Schedule Variance Always Indicates That the Project Is
Solved

An Undesirable Schedule Variance Always Indicates That the Project Is

Question 89

Question 89

True/False

An undesirable schedule variance always indicates that the project is running behind schedule.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q84: A Cost / Schedule graph can be

Q85: A project manager learns that his project

Q86: A "rubber baseline" occurs when, in an

Q87: Taking action in the four steps for

Q88: The start of a task may be

Q90: The value that tells you how much

Q91: In some cases, conditions or scope can

Q92: Deciding what data to collect, collecting the

Q93: A project control system allows for comparing

Q94: A project can have a negative schedule

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines