Given the project plan shown below, for each task assume that the best case duration is 80% of the most likely duration, and the worst case duration is 150% of the most likely duration.What is the expected completion time for the critical path?
A) 34 days
B) 21.0 days
C) 35.7 days
D) 22.1 days