Multiple Choice
For a project with many task paths of near equal length, the best way to estimate the probabilities associated with project completion is:
A) Estimate the probability for the critical path
B) Multiply the probabilities of all paths
C) Use simulation to model the project
D) Calculate the joint probability of project completion