Multiple Choice
A list of topics to be covered during a meeting that shows the running time allocated to and the person(s) responsible for leading the discussion for each topic is referred to as a
A) PERT chart.
B) program schedule.
C) Gantt chart.
D) time-based agenda.
E) action-item list.
Correct Answer: