    Given This Information About Activity 3-4: ES = 10, EF
Solved

Given This Information About Activity 3-4: ES = 10, EF

Question 93

Question 93

Multiple Choice

Given this information about activity 3-4: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is


A) 0.
B) 1.
C) 5.
D) 6.
E) 11.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q88: Activity C has an early start time

Q89: The basis for use of the beta

Q90: The higher the node number, the longer

Q91: Consider the portion of a project depicted

Q92: There are four activities on the critical

Q94: Deterministic networks use three time estimates-shortest, most

Q95: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q96: The main function of dummy activities is

Q97: Which of the following is not characteristic

Q98: A project is represented by the following

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines