Multiple Choice
Given this information about activity 3-4: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is
A) 0.
B) 1.
C) 5.
D) 6.
E) 11.
Correct Answer:

Verified
Correct Answer:
Verified