Multiple Choice
Which of the following statements is true about a critical path?
A) It consists of activities for which early start time equals late start time.
B) The total time of activities on the path take the longest time.
C) There is no slack in the activities along the critical path.
D) All of the above.
Correct Answer:

Verified
Correct Answer:
Verified
Q6: In project management,a work breakdown structure is<br>A)
Q7: Project managers can accept some (minimal)slack on
Q8: CPM methods should be used when the
Q9: Which of the following subjects are NOT
Q10: Consider the following definitions of slack: #1
Q12: Following the work breakdown structure,which activity is
Q13: The advantage(s)that the Gantt chart has over
Q14: Given the information above,what is the project
Q15: Which of the following statements is correct?<br>A)
Q16: The critical path of the following network