____ Involves Identifying the Specific Activities That the Project Team

Question 20

Multiple Choice

____ involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.


A) Defining activities
B) Sequencing activities
C) Estimating activity resources
D) Estimating activity durations

Correct Answer:

verifed

Verified