Solved

Outputs from ____ Include Work Performance Measurements,organizational Process Assets Updates,change

Question 22

Multiple Choice

Outputs from ____ include work performance measurements,organizational process assets updates,change requests,project management plan updates,and project document updates.


A) estimating activity durations
B) developing schedules
C) controlling the schedule
D) estimating activity resources

Correct Answer:

verifed