____ Use(s)probabilistic Time Estimates-Duration Estimates Based on Using Optimistic,most Likely,and
Multiple Choice
____ use(s) probabilistic time estimates-duration estimates based on using optimistic,most likely,and pessimistic estimates of activity durations-instead of one specific or discrete duration estimate.
A) Critical Path Analysis
B) Gantt charts
C) Critical Chain Scheduling
D) PERT
Correct Answer:

Verified
Correct Answer:
Verified