    In a ____ Relationship,the "From" Activity Must Finish Before the "To
Solved

In a ____ Relationship,the "From" Activity Must Finish Before the "To

Question 19

Question 19

Multiple Choice

In a ____ relationship,the "from" activity must finish before the "to" activity can start.


A) start-to-start
B) finish-to-start
C) finish-to-finish
D) start-to-finish

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q14: Schedule performance can be estimated by subtracting

Q15: What are the basic reasons for creating

Q16: Most projects have one path through a

Q18: A(n)_ is a schematic display of the

Q20: _ involves identifying the specific activities that

Q21: It only takes one activity to complete

Q22: Outputs from _ include work performance measurements,organizational

Q23: _ use(s)probabilistic time estimates-duration estimates based on

Q24: By using the PERT weighted average for

Q44:  The _ is a tabulation of activities

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines