Solved

A Simple Sequential Project (Each Task Must Be Completed Before

Question 18

Multiple Choice

A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below: A simple sequential project (each task must be completed before the next one can begin)  has the time estimates (in days)  shown below:   What is the probability that the project shown in Exhibit 15S-5 will be completed within 8.5 days? (Choose the closest answer.)  A) 80 percent B) 20 percent C) 75 percent D) 5 percent What is the probability that the project shown in Exhibit 15S-5 will be completed within 8.5 days? (Choose the closest answer.)


A) 80 percent
B) 20 percent
C) 75 percent
D) 5 percent

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions