Multiple Choice
Given the tasks, estimated durations, and crash costs shown below, if the benefit to crash the project by each day is a maximum of $750, how many days would it be worthwhile to crash the project?
A) 0
B) 1
C) 2
D) 3
E) 4
Correct Answer:

Verified
Correct Answer:
Verified