Given the Earliest and Latest Finish Times for Each of These

Question 59

Essay

Given the earliest and latest finish times for each of these activities, what are the activity lengths?
 Activity  EF  LF  Predecessors  A 33 B 1010 A  C 513 A  D 1818 B  E 1518 B  F 1119 C  G 819 C  H 2323 D, E  I 1523 F, G  J 2424 H, I \begin{array} { | c | c | c | c | } \hline \text { Activity } & \text { EF } & \text { LF } & \text { Predecessors } \\\hline \text { A } & 3 & 3 & \cdots \\\hline \text { B } & 10 & 10 & \text { A } \\\hline \text { C } & 5 & 13 & \text { A } \\\hline \text { D } & 18 & 18 & \text { B } \\\hline \text { E } & 15 & 18 & \text { B } \\\hline \text { F } & 11 & 19 & \text { C } \\\hline \text { G } & 8 & 19 & \text { C } \\\hline \text { H } & 23 & 23 & \text { D, E } \\\hline \text { I } & 15 & 23 & \text { F, G } \\\hline \text { J } & 24 & 24 & \text { H, I } \\\hline\end{array}

Correct Answer:

verifed

Verified

\[\begin{array} { | c | c | }
\hline \t...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions