Multiple Choice
Under ASPE, the profession requires that the percentage-of-completion method be used when certain conditions exist. Which of the following is NOT one of those necessary conditions?
A) Estimates of progress toward completion, revenues, and costs are reasonably dependable.
B) The contractor can be expected to perform the contractual obligation.
C) The buyer can be expected to satisfy some of the obligations under the contract.
D) The contract clearly specifies the enforceable rights of the parties, the consideration to be exchanged, and the manner and terms of settlement.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: When a company sells a bundle of
Q3: Cost estimates on a long-term contract may
Q4: Concessionary or abnormal terms may<br>A) reflect that
Q5: Timing of revenue recognition/percentage of completion<br>Crush
Q6: Reporting of gross or net revenues<br>Discuss three
Q7: Use the following information for the
Q8: Percentage-of-completion and completed-contract methods<br> On June 15,
Q9: Bluegrass Builders Ltd. Is using the
Q10: The earnings process<br>A) is the same for
Q11: The most popular input measure used to