Essay
The Chester Table Company mass produces quality end tables for motels. They produce 5,000 end tables per week. The owner is trying to determine how many workers he needs. The workers work 40 hours per week but are idle about three percent of the time because of the cleaning of their area. Their performance rating is equal to one. The owner has developed these time standards for operations per table:
Transporting the table through the plant = 2 minutes
Table top = 10 minutes
One leg = 4 minutes
Finishing = 5 minutes
a. How long does it take (in minutes) to produce one table?
b. What is the labor standard (in minutes) for this operation?
c. What is the minimum number of workers needed to produce 5000 tables in one week?
Correct Answer:

Verified
a. Cycle time for one table = 2 + 10 + 4...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q8: Consider the following time study data.
Q9: Allowances include time for all of the
Q10: A performance rating factor (PRF) of 130
Q11: A job had a normal time of
Q12: The _ states that the cost of
Q14: Determine the sample size for the following
Q15: The manager at a sewing factory uses
Q16: Based on data from a work-sampling study,
Q17: Explain the concept of learning curves using
Q18: A company manufactures tractors and lawnmowers. They