The manager at a sewing factory uses a piece?rate pay system. She has just received an order for 600 dresses from a discount house downtown. She is trying to figure out what her costs are for the project. She has conducted a time study and found the following times for operations:
2 minutes to sew one sleeve
3 minutes to sew body of the dress
3.5 minutes to hem all unfinished edges
1 minute to attach the collar
3 minutes to attach all buttons
The workers must sit idle while they wait for supplies on the conveyor belt for an average of 30 seconds. Their performance rating is equal to one. She pays the workers $6.00 per hour.
a. What is the allowance factor for the operation?
b. What is the labor standard (in minutes) per dress?
c. What is the labor cost per dress?
d. What is the labor cost for the entire order of 600 dresses?
Correct Answer:

Verified
a. Cycle time = 2(2) + 3 + 3.5 + 1 + 3 =...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q10: A performance rating factor (PRF) of 130
Q11: A job had a normal time of
Q12: The _ states that the cost of
Q13: The Chester Table Company mass produces quality
Q14: Determine the sample size for the following
Q16: Based on data from a work-sampling study,
Q17: Explain the concept of learning curves using
Q18: A company manufactures tractors and lawnmowers. They
Q19: A yacht manufacturer signed a contract to
Q20: Which of the following is NOT a