Multiple Choice
Latest start time is calculated by
A) subtracting the activity's estimated duration from the activity's succeeding activity's latest finish time: LS = LF succeeding activity - Estimated Duration.
B) adding the activity's estimated duration to the predecessor of the activity's latest start time: LS = LS predecessor + Estimated Duration.
C) subtracting the activity's estimated duration from the activity's latest finish time: LS = LF - Estimated Duration.
D) adding the activity's estimated duration to the activity's latest finish time: LS = LF + Estimated Duration.
Correct Answer:

Verified
Correct Answer:
Verified
Q35: Throughout a project, changes may occur that
Q36: One way to determine which activities make
Q37: Describe the agile project management for a
Q38: Free slack is the amount of time
Q39: The actual finish time of an activity<br>A)
Q41: The overall window of time in which
Q42: Total Slack is sometimes called<br>A) drift.<br>B) ride.<br>C)
Q43: When considering the availability of resources, it
Q44: When planning the project, it is important
Q45: Project management is a proactive approach to