True/False
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q60: A project's duration can be reduced by:<br>A)Shortening
Q61: Use the values in the table
Q62: The length of time expected to complete
Q63: An activity has an optimistic time estimate
Q64: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network
Q66: Which technique would accelerate the completion of
Q67: What is the slack time for
Q68: One approach to reducing project length would
Q69: What are three methods of duration estimation
Q70: Hammock activities allow:<br>A)Project managers to streamline the