Question 36

Multiple Choice

A project consists of four activities with information as shown in the table.What is the overall variance of the project?  Activity  Predecessor  Length  Variance  A 104 B  A 123 D  B 165 C 146\begin{array} { | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Length } & \text { Variance } \\\hline \text { A } & - & 10 & 4 \\\hline \text { B } & \text { A } & 12 & 3 \\\hline \text { D } & \text { B } & 16 & 5 \\\hline & \text { C } & 14 & 6 \\\hline\end{array}


A) 4.24
B) 8.41
C) 18
D) 24