menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain
  5. Question
    A Project Consists of Four Activities with Information as Shown
Solved

A Project Consists of Four Activities with Information as Shown

Question 46

Question 46

Multiple Choice

A project consists of four activities with information as shown in the table.What is the overall standard deviation of the project's duration? A project consists of four activities with information as shown in the table.What is the overall standard deviation of the project's duration?   A)  6.2 B)  4.1 C)  2.8 D)  5.1


A) 6.2
B) 4.1
C) 2.8
D) 5.1

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q31: The legal department is needed to review

Q41: Use the project information in the

Q44: A project is represented by the

Q45: A project consists of four consecutive

Q47: A project is represented by the

Q51: A project is represented by the

Q57: Picture yourself as a project manager intent

Q65: All of these happen during the sprint

Q70: Create a 5-activity example and use it

Q99: Extreme programming advocates a large development staff,several

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines