Multiple Choice
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology?
A) 3.5 days
B) 2.5 days
C) 1.5 days
D) 0.5 days
Correct Answer:

Verified
Correct Answer:
Verified