Consider the Project That Is Neatly Summarized in This Table

Question 19

Multiple Choice

Consider the project that is neatly summarized in this table.What are the highest priority activities when using the most resources required leveling heuristic?  Activity  Duration  Predecessors  Workers Required  A 83 B 24 D 6 A 5 E 7 B 6\begin{array} { | l | l | l | l | } \hline \text { Activity } & \text { Duration } & \text { Predecessors } & \text { Workers Required } \\\hline \text { A } & 8 & - & 3 \\\hline \text { B } & 2 & - & 4 \\\hline \text { D } & 6 & \text { A } & 5 \\\hline \text { E } & 7 & \text { B } & 6 \\\hline\end{array}


A) E and B
B) C and E
C) C and D
D) B and D