Multiple Choice
A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs:
A) On days 19 through 20 for an early start schedule.
B) On days 17 through 20 for a late start schedule.
C) On days 13 through 18 for an early start schedule.
D) On days 21 through 22 for a late start schedule.
Correct Answer:

Verified
Correct Answer:
Verified