Create a Resource Loading Chart Using Early Start Times for the Project

Question 24

Essay

Create a resource loading chart using early start times for the project described by this table.  Activity  Time  Predecessor  Task A144B25C4 A5D9 B4E8C5F2C3H3D2K5 F,G4L1E3\begin{array} { | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } & \text { Task } \\\hline \mathrm { A } & 14 & - & 4 \\\hline \mathrm { B } & 2 & - & 5 \\\hline \mathrm { C } & 4 & \mathrm {~A} & 5 \\\hline \mathrm { D } & 9 & \mathrm {~B} & 4 \\\hline \mathrm { E } & 8 & \mathrm { C } & 5 \\\hline \mathrm { F } & 2 & \mathrm { C } & 3 \\\hline \mathrm { H } & 3 & \mathrm { D } & 2 \\\hline \mathrm { K } & 5 & \mathrm {~F} , \mathrm { G } & 4 \\\hline \mathrm { L } & 1 & \mathrm { E } & 3 \\\hline\end{array}

Correct Answer:

verifed

Verified

The early start times appear in this tab...