Use the Information in the Table and Assume That a Worker

Question 21

Multiple Choice

Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?   A)  Week 4 B)  Week 5 C)  Week 6 D)  Week 7


A) Week 4
B) Week 5
C) Week 6
D) Week 7

Correct Answer:

verifed

Verified