Solved

Use the Information in the Table and Assume That a Worker

Question 56

Multiple Choice

Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?  Activity  Duration  Predecessor A5 days B4 days AC5 days  A D6 days BE6 days C,DF6 days E\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Duration } & \text { Predecessor } \\\hline \mathrm { A } & 5 \text { days } & - \\\hline \mathrm { B } & 4 \text { days } & \mathrm { A } \\\hline \mathrm { C } & 5 \text { days } & \text { A } \\\hline \mathrm { D } & 6 \text { days } & \mathrm { B } \\\hline \mathrm { E } & 6 \text { days } & \mathrm { C } , \mathrm { D } \\\hline \mathrm { F } & 6 \text { days } & \mathrm { E } \\\hline\end{array}


A) Week 6
B) Week 2
C) Week 4
D) Week 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions