Solved

A Project Consists of Six Activities (All Times Are Given

Question 58

Essay

A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule.
 Activity  Activity time  Activity Cost  Predecessor K10140L864 K,MM1296N6120MP14168 LQ12144N\begin{array} { | l | l | l | l | } \hline \text { Activity } & \text { Activity time } & \text { Activity Cost } & \text { Predecessor } \\\hline \mathbb { K } & 10 & 140 & \\\hline \mathrm { L } & 8 & 64 & \mathrm {~K} , \mathrm { M } \\\hline \mathrm { M } & 12 & 96 & \\\hline \mathbb { N } & 6 & 120 & \mathbb { M } \\\hline \mathbb { P } & 14 & 168 & \mathrm {~L} \\\hline \mathbf { Q } & 12 & 144 & \mathbb { N } \\\hline\end{array}

Correct Answer:

verifed

Verified

Highest resource usage occurs during day...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions