A Project Consisting of Six Activities Is Shown in the Table.If

Question 27

Multiple Choice

A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements? A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements?   A)  Day 21 B)  Day 18 C)  Day 24 D)  Day 15


A) Day 21
B) Day 18
C) Day 24
D) Day 15