Multiple Choice
Schedule control involves four steps. Place these steps in their proper order by stating the letter sequence of their proper order.
A) A,B,C,D
B) A,D,C,B
C) D,A,C,B
D) D,A,B,C
Correct Answer:

Verified
Correct Answer:
Verified