Multiple Choice
Cost variance CV) is _____.
A) earned value minus actual cost
B) earned value minus planned value
C) the ratio of earned value to planned value
D) the ratio of earned value to actual cost
E) budget at completion minus the earned value
Correct Answer:

Verified
Correct Answer:
Verified