Multiple Choice
The unit of time used to develop the activity duration is a function of:
A) the relationship dependence of project activities.
B) the skill level of the project team.
C) the level of detail needed by the user of the schedule.
D) the phase of the project.
E) the availability of project resources.
Correct Answer: