Multiple Choice
Resource calendars become important tools when:
A) resources are aplenty.
B) participants are not interacting at the same time.
C) changes must be made to the schedule.
D) the scope of work is not well known.
E) changes are not documented in the agenda.
Correct Answer:

Verified