Multiple Choice
The process for developing the project logic involves identifying the _____ and _____.
A) lag time; lead time
B) start; finish
C) dependency; autonomy
D) predecessors; successors
E) derivatives; antecedents
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q18: Resource calendars become important tools when:<br>A) resources
Q19: The unit of time used to develop
Q20: If any activity on the critical path
Q21: _ the schedule is a term used
Q22: Which of the following is true about
Q24: Most activities in a network diagram have
Q25: The _ is the sequence of activities
Q26: All of the following are techniques project
Q27: A WBS can be decomposed, that is,
Q28: Open Source software is always a better