Multiple Choice
Which of the following is true about a work breakdown structure WBS) ?
A) Developing a WBS begins by defining and developing lists of all activities needed to accomplish the work of the project.
B) The first draft of the WBS includes activities at the low-level.
C) The first draft of the WBS typically includes the minor activities required to accomplish the deliverables identified in the project scope of work.
D) The WBS is decomposed to the level that the client needs to control the project.
E) Typically, smaller and simpler projects require more detailed WBS.
Correct Answer:

Verified
Correct Answer:
Verified
Q17: You cannot miss an important constraint if
Q18: Resource calendars become important tools when:<br>A) resources
Q19: The unit of time used to develop
Q20: If any activity on the critical path
Q21: _ the schedule is a term used
Q23: The process for developing the project logic
Q24: Most activities in a network diagram have
Q25: The _ is the sequence of activities
Q26: All of the following are techniques project
Q27: A WBS can be decomposed, that is,