Multiple Choice
The _____ is the sequence of activities through the network that results in the latest completion date of the project.
A) master schedule
B) alignment process
C) milestone schedule
D) rough order of magnitude
E) critical path
Correct Answer:

Verified
Correct Answer:
Verified