Multiple Choice
All of the following are techniques project managers can use to accelerate the project schedule, EXCEPT:
A) improving quality.
B) reassigning resources.
C) changing the scope.
D) adding additional resources.
E) using contingency resources
Correct Answer:

Verified
Correct Answer:
Verified