menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 1
  4. Exam
    Exam 9: Resource Allocation
  5. Question
    The Tasks That Logically Precede a Particular Task in Time
Solved

The Tasks That Logically Precede a Particular Task in Time

Question 1

Question 1

Multiple Choice

The tasks that logically precede a particular task in time are referred to as __________.


A) successors
B) followers
C) predecessors
D) priorities

Correct Answer:

verifed

Verified

Related Questions

Q2: If a contradiction or conflict between constraints

Q3: Suggest some options for leveling the load

Q4: Match the following priority rules with additional

Q5: The principal reason why a project manager

Q6: List some of the common priority rules

Q7: If a predecessor activity finishes early,will the

Q8: Match the following priority rules with their

Q9: The _ heuristic provides a general solution

Q10: If the crash cost is $2,500,the normal

Q11: In some situations,two activities are scheduled to

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines